Cradle to grave: how we build, sell, deliver and retire our service for one customer. The nominal version, as a Gantt chart.
BrianCepeli
MatteoFornara
AlessandroGazzara
PietroGilli IncantalupoThe same unit as our techno-economic assessment (TEA): yearly fee, yearly renewal. Times the customers we win each year, it gives the startup.
As in the TEA. Year 1 in full detail; years 2–5 repeat the same functions.
The pilot converts, the customer renews, the suppliers answer. The deviations come later, in Klarisk.
with the fewest functional interfaces
of each subsystem
nominal, start-up, shut-down, grade change, maintenance, emergency
what the system needs to move from one state to the next
input, system, output, each with its protective function; sensor, logic, actuator
The pilot kick-off (D.1) needs the signed order and the MVP. Both arrive on 15 Jun 27.
By design, so the order arrives the day the MVP is ready. No margin: an MVP delay moves the first income.
61 working days from first contact to signature: in 31 of them we wait for the customer or the suppliers.
Before the MVP: 17 interviews on facts (spend on protection, last disruption, who signs), 2 letters of intent, then a go / no-go (B.0).
The approval is decomposed to level 3. The CFO's evaluation (C.3.2) is a red flag: its time and odds are not ours.
Pilot and subscription terms together. Vendor registration runs in parallel, so it does not delay the order.
First a map from ERP, public data and typical recovery times (D.3). Then the sensitivity picks the 3–5 data that can change the choice.
8 working days on the critical path, done by third parties. A reminder and typical values protect them.
Data quality (D.2.3) and four-eyes review (D.6), each split into sensor, logic and actuator.
The contract was reviewed with the pilot order: the customer only chooses level and start date. It was 14 days.
It no longer blocks the signature. Signed 4 Aug, start 30 Aug, after the summer closure; yearly fee invoiced in advance.
Within our 10-day promise. The recurring ERP export (F.2) is the part we know least: every ERP is different.
Every quarter the engine recalculates; the analyst steps in only if the choice changes (G.1.1.4). Q1 is split into 6 steps (level 4).
A start-to-start link: the CFO prepares the budget in October, our allocation comes in October.
Decision register (G.1.1.6), follow-up 30 days after the decision, health check 120 days before.
31 of the 61 working days on the critical path wait for the customer or the suppliers.
Double link on the pilot kick-off, zero slack: an MVP delay moves pilot, contract and fee.
Budget cycle and deferred start: the signature arrives, the fee may not.
If the protections are not implemented (G.3.5), there is little to show at renewal.
Into map, proposal and decision: two checks in series (D.2.3 and D.6).
How many events per customer per year? It drives the analyst's hours.
Interviews ask facts, not opinions, and a commitment.
target: 2 letters of intentBefore, the interviews changed nothing in the process.
no confirmation, no engineFirst the map, then only the 3–5 data that change the choice.
fewer questions to suppliersPilot and subscription terms in the same contract.
decision: 14 → 8 working daysThe budget moves the start; it no longer blocks the signature.
signature and start decoupledNo longer deducted from the first yearly fee: its map is worth its price.
same as the TEA and the pitchCFO decision, implementation by the customer, renewal.
4 new protective functionsThe method asks for the fewest interfaces.
2 interfaces fewerWith 260 working days a year, the anniversary drifted.
renewal every 30 AugustReviewing every update was consulting; the register proves the value.
7.5 vs 10.5 person-days a year| Type | What it is | Elementary functions |
|---|---|---|
| S · System | Work of Nexora, of the engine or of the team | 62 |
| I · Input | What comes from outside: customer, suppliers, data providers | 14 |
| O · Output | What we deliver, or what the customer does with our decision | 11 |
| Q · Protective | Checks and barriers that protect the function they are linked to | 28 |
| W · Standby | Designed and ready, started only by an event: dashed over their active period | 8 |
| M · Milestone | Step between two states | 16 |
| Total | Human 38 · technological 57 · organisational 28 (milestones excluded) | 139 |
| They protect | Protective functions (Q) |
|---|---|
| The engine is right | A.1.4 data model checked on the simulated company · A.6.1 regression tests · A.6.2 plausibility check against a benchmark · G.4.3 tests at each release |
| The customer's data | D.2.3 quality check in the pilot · D.4.4 reminder to suppliers · D.4.5 typical values for missing answers · G.1.1.2 check at each update |
| The decision we deliver | D.6 four-eyes review · G.1.1.4 change check · G.3.3 review of the budget split · F.6 go-live check |
| Conversion and renewal | D.4.6 mid-pilot check-in · G.1.1.6 decision register · G.3.6 follow-up at 30 days · G.6 health check at −120 days |
| The team's time | B.3.3 qualification gate before any on-site visit · B.0.3 go / no-go before the decision engine |
| Data and liability | C.4 NDA and data agreement · A.6.3 GDPR set-up · G.4.4 backups · I.4 export confirmed before deletion · I.5 certified deletion · Z.4 GDPR · Z.2 insurance |
| The payment | E.6 reminder if the yearly fee is late (a standby function, like Z.6 incident response) |
| Function | Sensor | Logic | Actuator |
|---|---|---|---|
| D.2.3 · Data quality check (pilot) | Validation rules on the ERP import and the public data | Completeness and consistency thresholds | The analyst asks for missing data or uses typical values |
| D.6 · Four-eyes review | A second analyst reads map and proposal | Plausibility checklist: benchmarks, outliers | Release, or back to D.5 |
| G.2 · Event watch | Hazard and weather alerts at supplier sites, credit-score drops, lead times growing in the ERP | Threshold rules: the event falls in a site's hazard zone or the score drops | Re-run the model and warn the buyer within 2 working days |
| G.1.1.4 · Change check (quarterly) | The engine compares the new choice with the previous one | Threshold: protection of at least one part, or budget beyond a tolerance, changes | Automatic report if nothing changes; otherwise the analyst reviews |
| G.6 · Check before renewal (organisational) | Decision register and use of the service | Threshold: few protections implemented, or low use | Action plan with the buyer before the value review |
| H.1 · Renewal trigger | Contract calendar | 60-day rule | Value review with the CFO (H.2) |
In the event watch the sensor (G.2.1) always works, so it is a system function; logic and actuator (G.2.2, G.2.3) start only with an event, so they are standby functions.
| Step | When it happens | What starts |
|---|---|---|
| S2 → S1 | Negative qualification (B.3.3) | The contact goes back to the channels' pool |
| S3 → S7 | The pilot does not become a contract (E.2.1) | Short decommissioning: export and deletion of the pilot data (I.3–I.5); new contact at the next budget |
| S3 → S4, deferred start | This year's budget is closed (E.2.2) | Sign now; start and invoice with the new budget year |
| S5 → S5e → S5 | An alert hits a supplier | G.2.1 → G.2.2 → G.2.3, then back to the quarterly cycle |
| S5 → S5m → S5 | Engine release | G.4.3; the service stays on, the release passes the regression tests |
| S6 → S7 | The customer cancels at renewal (H.2) | Full decommissioning (I.1–I.8) before the end of the horizon |
| S5 → S8 → S5 | Security incident | Z.6: access suspended, customers and Garante notified within 72 hours; restart after checks |
| D.6 → D.5 | The four-eyes review rejects the map | Back to updating the map (2–3 more days) |
| ID | Function | Earliest start | Latest start | Slack (wd) |
|---|---|---|---|---|
| A.4.5 | Sensitivity & value of information | 20 May 27 | 24 May 27 | 2 |
| C.3.4 | Legal review of one contract (pilot + subscription terms) | 2 Jun 27 | 4 Jun 27 | 2 |
| D.2.2 | Public hazard & credit data at supplier addresses | 23 Jun 27 | 25 Jun 27 | 2 |
| D.4.4 | Reminder by the buyer | 8 Jul 27 | 13 Jul 27 | 3 |
| A.6.2 | Plausibility check vs benchmark (MGI 1 in 3.7 yrs) | 3 Jun 27 | 9 Jun 27 | 4 |
| C.4 | NDA & data processing agreement (pilot + subscription) | 2 Jun 27 | 8 Jun 27 | 4 |
| D.4.6 | Mid-pilot check-in with buyer & CFO (expectations, budget timing) | 6 Jul 27 | 13 Jul 27 | 5 |
| A.1.3 | Map public data sources (ISPRA, INGV, credit scores) | 4 Jan 27 | 12 Jan 27 | 6 |
| B.0.1 | 17 interviews on facts: spend, last disruption, who signs | 4 Jan 27 | 27 Jan 27 | 17 |
| B.0.3 | Go / no-go: problem confirmed, keep building? | 1 Mar 27 | 24 Mar 27 | 17 |
| A.2.2 | Geocode supplier sites + hazard lookup (IdroGEO, INGV) | 26 Jan 27 | 19 Feb 27 | 18 |
| A.3.4 | Exposure map & criticality ranking | 25 Mar 27 | 22 Apr 27 | 20 |
| A.4.3 | Protection cost library (stock, 2nd source, insurance) | 25 Mar 27 | 22 Apr 27 | 20 |
| A.5.1 | Exposure-map report (pilot deliverable) | 6 Apr 27 | 4 May 27 | 20 |
| A.5.3 | Web dashboard & user access | 6 Apr 27 | 4 May 27 | 20 |
| A.6.3 | Security & GDPR set-up (EU hosting, backups, DPA) | 4 May 27 | 1 Jun 27 | 20 |
| A.2.3 | Credit-risk data connector (Cerved / CRIF) | 26 Jan 27 | 25 Feb 27 | 22 |
| A.2.4 | Questionnaire web form & answer import | 26 Jan 27 | 20 May 27 | 82 |
| Item | Person-days | What it includes |
|---|---|---|
| Each pilot, converted or not | 10.6 | Qualification, visit, proposal, delivery, review, presentation, offer |
| Onboarding a new customer | 6.5 | Scope extension, ERP export, thresholds, sensors, training, check |
| One active customer for a year | 7.5 (10.5 without review by exception) | Updates, events, budget, support, value review and renewal |
| Fixed work of the company per year | 62 | Channels, parameter library, releases, administration |
Four full-time founders ≈ 880 person-days a year [assumption]. Pilots, onboarding, customers and fixed work take 30% (year 2) to 52% (year 5) of the time [estimate]: the limit is finding customers, not time.
| Function | Variable | Value today | Label |
|---|---|---|---|
| B.1 | Pilots per year found by the founders | 1–4 in year 1, then 3–8 | [assumption] |
| B.0 | Interviews confirming the problem; letters of intent | 17 interviews; target 2 letters | [to verify] |
| B.3.3, C.3.2 | Share of contacts that qualify and accept the pilot | to estimate | [to verify] |
| C.1 · C.2 | Travel per pilot · pilot price | €300–600 · €2,500 | [assumption] |
| D.4.3 | Suppliers' response rate | to estimate | [to verify] |
| D.8.2 | Days to collect the payment | 30 | [assumption] |
| E.1 | Yearly fee | €6–15k, most likely €9k | [assumption] |
| E.2.1 | Pilot → contract conversion | 40–80% | SaaStr (industry), lowered |
| B.2 → E.3 | Sales cycle | 85 days nominal; 124 as reference | [estimate]; industry |
| F | Onboarding effort per customer (≤ 10 working days) | 6.5 person-days | [assumption] |
| G.1.1.4 | Updates needing the analyst · cloud per customer | 1 in 4 · €200 a year | [assumption] |
| G.2 | Events per customer per year | to estimate | [to verify] |
| G.5 · H.2 | Growth of staying customers · renewal | 0–8% · 80–92% a year | Benchmarkit (industry) |
| Z | Fixed costs | €15k in year 1, then €9k | [assumption] |
| Function | Deviation | Effect on the process | Variable for the model |
|---|---|---|---|
| A | MVP development is late | Moves D.1 and with it pilot, conversion and first fee (no slack) | Days of MVP delay |
| B.0.3 | No letter of intent, few confirmations | Negative go / no-go: revise the offer before building the decision engine | Letters of intent obtained |
| B.1 | A channel brings no contacts | The first contact (B.2) comes later | Contacts per channel |
| B.3.3 | Negative qualification | Back to S1; time spent without a pilot | Share of qualified contacts |
| C.3.2 | The CFO postpones or refuses | Later pilot order, or no pilot | Chance of a yes; time (three estimates) |
| D.4.3 | Suppliers do not answer, or answer badly | Typical values with wider ranges (D.4.5); a less precise map | Response rate |
| D.6 | The review rejects map or proposal | Back to D.5, 2–3 more days | Share of rejected reviews |
| E.2.1 | The customer does not convert | S3 → S7 with short decommissioning | Conversion 40–80% |
| E.5 | The yearly fee is paid late | Reminder (E.6); cash arrives later | Days to collect |
| E.2.2 | This year's budget is closed | Sign now, start and fee with the new year | Share of deferred starts |
| F.2 | The ERP has no standard export | Onboarding beyond 10 days | Days of onboarding |
| G.2 | Alert on a supplier | Event re-run and analyst hours | Events per customer per year |
| G.3.5 | The customer does not implement | Little value to show at renewal | Share of decisions implemented |
| H.2 | The customer cancels | S6 → S7 before the end of the horizon | Renewal 80–92% a year |
| Z.6 | Security incident | Emergency shut-down, notice within 72 hours | Incident frequency [to verify] |