Functional analysis of our core business process

Cradle to grave: how we build, sell, deliver and retire our service for one customer. The nominal version, as a Gantt chart.

Brian CepeliBrianCepeli
Matteo FornaraMatteoFornara
Alessandro GazzaraAlessandroGazzara
Pietro Gilli IncantalupoPietroGilli Incantalupo
Decision Engineering · Politecnico di Milano · prof. S. Colombo · 30 October 2026
What we analyse

One customer, cradle to grave: the process we cannot live without

OnceBuild the enginethe MVP: data, model, reports
Per customerSellchannels, then a paid pilot
Per customerPilotexposure map in 26 working days
Per customerConvert & onboardcontract, then go-live
Every year · 5 yearsServe & renewquarterly updates, yearly budget
At the endRetireexport, delete, certificate
Every pilot and every quarterly update is a production run:
ERP + public data quality check model review report customer decision
Functional unitOne customer for one year

The same unit as our techno-economic assessment (TEA): yearly fee, yearly renewal. Times the customers we win each year, it gives the startup.

Horizon5 years of the customer's life

As in the TEA. Year 1 in full detail; years 2–5 repeat the same functions.

VersionNominal: the designer's view

The pilot converts, the customer renews, the suppliers answer. The deviations come later, in Klarisk.

Reference customer: a machine builder in our target, Standard tier (up to 200 parts, €10k a year), standard ERP export. Four full-time founders, unpaid for two years. Calendar: working days from Mon 4 Jan 2027. All [assumptions]02 / 17
How we did it

The five steps of the HoRAM functional analysis

1
Subsystems

with the fewest functional interfaces

4subsystems, 6 interfaces
2
Processes

of each subsystem

24processes
3
States

nominal, start-up, shut-down, grade change, maintenance, emergency

12states
4
Steps between states

what the system needs to move from one state to the next

16milestones
5
Functions

input, system, output, each with its protective function; sensor, logic, actuator

177functions on 4 levels
Function types · the colours of our Gantt charts
System work of Nexora, the engine or the team
62
Input from outside: customer, suppliers, data
14
Output what we deliver, or what the customer does with it
11
Protective checks and barriers
28
Standby always ready, started by an event
8
Milestone step between two states
16
Human, technological, organisational · the 123 that are not milestones
57technological
38human
28organisational
Gantt computed from our model, not drawn by hand
S. Colombo, The Holistic Risk Analysis and Modelling (HoRAM) method, Safety Science 112 (2019) 18–37. Counts: the 139 elementary functions; human, technological, organisational: the 123 that are not milestones03 / 17
Steps 1–2 · subsystems and processes

Four subsystems, six interfaces, one common support

SS1Product & enginebuilds and keeps the engineFUNCTIONS A, G.4.2–3Data model & questionnaireData pipelineExposure engineDecision engineReports & interfaceVerification & validationEngine releasesSS3Service deliveryproduces the analysisFUNCTIONS D, GPilot: exposure mapQuarterly recalculationEvent watchAnnual budget allocationSS2Commercial & customerfrom first contact to the endFUNCTIONS B, C, E, F, H, ILead generationQualificationPilot saleConversionOnboardingRenewalDecommissioningSS4Company supporta common support to all · functions ZIncorporationAccounting & invoicesGDPR & securityCloud infrastructureInsuranceIncident responseengine andparametersA.7 · G.4.2–3real recoverytimes, anonymisedI.6 → G.4.2pilot orderand scopeC.5 · D.1 · F.1results anddecision registerD.7 · G.1.1.6 · H.2interview results become engine requirementsB.0.3 → A.4.1invoicesD.8 · E.4–5 · H.3 · I.7
SS4 gives everyone infrastructure and rules (cloud, GDPR, accounting): a common support, not counted as an interface. Sales and customer relationship stay together: same buyer and CFO from start to end, two interfaces fewer04 / 17
Steps 3–4 · states and steps between states

Every change of state is a milestone with a condition

S1 · START-UPProspectin the target marketS2 · START-UPQualified leadB.2 · 11 May 27S3 · START-UPPilot customerC.5 · 15 Jun 27S4 · START-UPOnboardingE.3 · 4 Aug 27S5 · NOMINALSteady serviceF.7 · 10 Sep 27S5b budget cycleS5e event modeS5m maintenanceS6 · GRADE CHANGERenewalH.1 · 60 days beforeS7 · SHUT-DOWNDecommissionI.1 · 30 Aug 32S0 · START-UPProduct in developmentA.7 MVP ready15 Jun 27nominal step = milestone in the Ganttnot nominal: probabilities in KlariskY5.5 closure notice → I.1 end of contractH.3 renewedevery 30 AugH.2 cancelsB.3.3 no-goE.2.1 pilot not convertedS8 · EMERGENCYShut-downZ.6 · notify within 72 h
State types from the course: start-up, nominal condition, grade change, maintenance, shut-down, emergency shut-down. Inside S5: S5b budget cycle (grade change), S5e event mode (abnormal), S5m engine release (maintenance)05 / 17
The Gantt · level 1

From the first line of code to the deleted data

Level-1 functions, nominal versiondurations in working days (wd)
202720282029203020312032A Develop the decision engine (MVP): 4 Jan 27 – 14 Jun 27, 116 working daysA.7 MVP ready: 15 Jun 27B Validate, generate & qualify leads: 4 Jan 27 – 7 Jun 27, 111 working daysB.2 Sales contact with the reference customer (LOI or channel): 11 May 27C Sell the paid pilot: 18 May 27 – 14 Jun 27, 20 working daysC.5 Pilot order signed: 15 Jun 27D Deliver the paid pilot (+ payment): 15 Jun 27 – 20 Aug 27, 49 working daysE Convert to subscription: 21 Jul 27 – 28 Sep 27, 50 working daysE.3 Subscription signed (annual, auto-renewal): 4 Aug 27E.4 Contract start: annual fee invoiced in advance: 30 Aug 27F Onboard the customer (<= 10 wd): 30 Aug 27 – 9 Sep 27, 9 working daysF.7 Go-live: 10 Sep 27G Deliver the service, year 1: 10 Sep 27 – 24 Aug 28, 250 working daysH Renew the subscription (year 1 > 2): 3 Jul 28 – 29 Aug 28, 42 working daysH.3 Auto-renewal & invoice year 2: 30 Aug 28Y2 Service year 2 (same functions as G + H): 30 Aug 28 – 29 Aug 29, 261 working daysY2.5 Value review & renewal (year 2 > 3): 30 Aug 29Y3 Service year 3 (same functions as G + H): 30 Aug 29 – 29 Aug 30, 261 working daysY3.5 Value review & renewal (year 3 > 4): 30 Aug 30Y4 Service year 4 (same functions as G + H): 30 Aug 30 – 29 Aug 31, 261 working daysY4.5 Value review & renewal (year 4 > 5): 1 Sep 31Y5 Service year 5 (same functions as G + H): 1 Sep 31 – 20 Aug 32, 255 working daysY5.5 End of horizon: closure notice (90 days before term): 1 Jun 32I Decommission the customer (end of lifecycle): 25 Aug 32 – 16 Sep 32, 17 working daysI.8 Customer lifecycle closed: 17 Sep 32Z Company support (continuous): 4 Jan 27 – 16 Sep 32, 1489 working daysMVP ready · 15 Jun 27pilot order · 15 Jun 27signed 4 Aug · start 30 Aug 27go-live · 10 Sep 27renewed · 30 Aug 2830 Aug 2930 Aug 301 Sep 31closed · 17 Sep 32← the first 9 months, zoomed in on the next slideADevelop the decision engine (MVP)116Red flagBValidate, generate & qualify leads111Red flagCSell the paid pilot20Red flagDDeliver the paid pilot (+ payment)49Red flagEConvert to subscription50Red flagFOnboard the customer9Red flagGDeliver the service, year 1250HRenew the subscription (year 1 → 2)42Y2Service year 2 (as G + H)261Y3Service year 3 (as G + H)261Y4Service year 4 (as G + H)261Y5Service year 5 (as G + H)255IDecommission the customer17ZCompany support (continuous)cont.
Level-1 functionMilestoneContains a red flag (a function we know least)
Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by hand. Bars D and E include the 30-day payment of the pilot invoice and of the yearly fee. Anniversaries are calendar dates, so they do not drift06 / 17
Interconnections · the first nine months

Two chains meet on the pilot, with zero slack

January – September 2027, level 2red = critical path to the signature
Jan 27FebMarAprMayJunJulAugSepA Build the MVP: 4 Jan 27 – 14 Jun 27, 116 working daysA.7 MVP ready: 15 Jun 27B.0.1 17 customer interviews: 4 Jan 27 – 26 Feb 27, 40 working daysB.0.2 Letters of intent (target 2): 1 Mar 27B.0.3 Go / no-go: keep building?: 1 Mar 27 – 1 Mar 27, 1 working daysB.1 Acquisition channels (3): 27 Apr 27 – 7 Jun 27, 30 working daysB.2 First contact: 11 May 27B.3 Qualify the lead: 11 May 27 – 17 May 27, 5 working daysC Sell the paid pilot: 18 May 27 – 14 Jun 27, 20 working daysC.5 Pilot order signed: 15 Jun 27D Deliver the pilot: 15 Jun 27 – 20 Aug 27, 49 working daysE Offer and decision: 21 Jul 27 – 28 Sep 27, 50 working daysE.3 Subscription signed: 4 Aug 27E.4 Contract start: 30 Aug 27F Onboard the customer: 30 Aug 27 – 9 Sep 27, 9 working daysF.7 Go-live: 10 Sep 27letters of intent→ approval odds15 Jun1 Mar11 May15 Jun4 Aug30 Aug10 Sep35 working daysABuild the MVPRed flagA.7MVP readyMB.0.117 customer interviewsSB.0.2Letters of intent (target 2)MB.0.3Go / no-go: keep building?QB.1Acquisition channels (3)Red flagB.2First contactMB.3Qualify the leadCSell the paid pilotRed flagC.5Pilot order signedMDDeliver the pilotRed flagEOffer and decisionRed flagE.3Subscription signedME.4Contract startMFOnboard the customerRed flagF.7Go-liveM
SummaryMilestoneCritical pathLogical linkStochastic conditioningRed flag
One function, two conditions

The pilot kick-off (D.1) needs the signed order and the MVP. Both arrive on 15 Jun 27.

Selling starts 35 days early

By design, so the order arrives the day the MVP is ready. No margin: an MVP delay moves the first income.

Zero slack on the red path

61 working days from first contact to signature: in 31 of them we wait for the customer or the suppliers.

Critical path = the functions with zero slack: if one of them is one day late, the signature (E.3) moves by one day. Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by hand07 / 17
A · How we build the product

The MVP in 116 working days, while we validate with customers

Develop the decision engine, January – June 2027levels 2 and 3
Jan 27FebMarAprMayJunA.1 Data model & questionnaire: 4 Jan 27 – 25 Jan 27, 16 working daysA.1.4 Check on simulated company: 20 Jan 27 – 25 Jan 27, 4 working daysA.2 Data pipeline: 26 Jan 27 – 16 Feb 27, 16 working daysA.3 Exposure engine: 17 Feb 27 – 5 Apr 27, 34 working daysA.4 Decision engine: 25 Mar 27 – 31 May 27, 48 working daysA.5 Reports & web dashboard: 6 Apr 27 – 2 Jun 27, 42 working daysA.6.1 Regression tests: 3 Jun 27 – 14 Jun 27, 8 working daysA.6.2 Plausibility vs benchmark: 3 Jun 27 – 8 Jun 27, 4 working daysA.6.3 Security & GDPR set-up: 4 May 27 – 17 May 27, 10 working daysA.7 MVP ready: 15 Jun 27B.0.1 17 interviews on facts: 4 Jan 27 – 26 Feb 27, 40 working daysB.0.2 Letters of intent (target 2): 1 Mar 27B.0.3 Go / no-go: keep building?: 1 Mar 27 – 1 Mar 27, 1 working daysZ.1 Incorporation, bank: 4 Jan 27 – 29 Jan 27, 20 working daysZ.2 Liability insurance: 1 Feb 27 – 5 Feb 27, 5 working days15 Jun1 MarA.1Data model & questionnaireA.1.4Check on simulated companyQA.2Data pipelineRed flagA.3Exposure engineA.4Decision engineRed flagA.5Reports & web dashboardA.6.1Regression testsQA.6.2Plausibility vs benchmarkQA.6.3Security & GDPR set-upQA.7MVP readyMB.0.117 interviews on factsSB.0.2Letters of intent (target 2)MB.0.3Go / no-go: keep building?QZ.1Incorporation, bankSZ.2Liability insuranceQ
SummarySystemProtectiveMilestoneCritical pathLogical linkRed flag
Critical path at level 3
  • A.1.1ERP export template
  • A.1.2Supplier questionnaire
  • A.1.4Check on simulated company
  • A.2.1ERP import with checks
  • A.3.1Part → supplier → site link
  • A.3.2Impact per site & cause
  • A.3.3Frequency per site & cause
  • A.4.1Event tree per option
  • A.4.2Monte Carlo simulation
  • A.4.4Best protection in budget
  • A.5.2Decision report for CFO
  • A.6.1Regression tests
  • A.7MVP ready
Development ≈ 120 person-days at the pace of about one full-time person; the rest of the team interviews customers, sets up the company and prepares sales [assumptions]. 116 wd ≈ 6 months, as in the preliminary TEA; three estimates: 100–116–180 wd. Full level 3: Backup A08 / 17
B–C · How we sell

Selling the pilot: 12 working days are in the customer's hands

From the channels to the pilot order, April – June 2027levels 2 and 3 · weekends shaded
26 Apr3 May10 May17 May24 May31 May7 Jun14 JunB.1.1 PoliMi network & mentors: 27 Apr 27 – 7 Jun 27, 30 working daysB.1.2 ADACI events (purchasing): 27 Apr 27 – 7 Jun 27, 30 working daysB.1.3 LinkedIn content: 27 Apr 27 – 7 Jun 27, 30 working daysB.2 First contact: 11 May 27B.3.1 Check fit (sector, size): 11 May 27 – 11 May 27, 1 working daysB.3.2 Discovery call: 12 May 27 – 14 May 27, 3 working daysB.3.3 Go / no-go gate: 17 May 27 – 17 May 27, 1 working daysC.1 Meeting: purchasing + CFO: 18 May 27 – 24 May 27, 5 working daysC.2 Pilot proposal + terms: 25 May 27 – 27 May 27, 3 working daysC.3.1 Buyer presents it inside: 28 May 27 – 1 Jun 27, 3 working daysC.3.2 CFO weighs price vs value: 2 Jun 27 – 8 Jun 27, 5 working daysC.3.3 New vendor registration: 4 Jun 27 – 10 Jun 27, 5 working daysC.3.4 Legal review, one contract: 2 Jun 27 – 8 Jun 27, 5 working daysC.3.5 Purchase order: 11 Jun 27 – 14 Jun 27, 2 working daysC.4 NDA & data agreement: 2 Jun 27 – 8 Jun 27, 5 working daysC.5 Pilot order signed: 15 Jun 27channel → approval odds11 May15 Jun12 working days in the customer's handsB.1.1PoliMi network & mentorsSRed flagB.1.2ADACI events (purchasing)SRed flagB.1.3LinkedIn contentSRed flagB.2First contactMB.3.1Check fit (sector, size)SB.3.2Discovery callSB.3.3Go / no-go gateQC.1Meeting: purchasing + CFOSC.2Pilot proposal + termsOC.3.1Buyer presents it insideIC.3.2CFO weighs price vs valueIRed flagC.3.3New vendor registrationIC.3.4Legal review, one contractIC.3.5Purchase orderIC.4NDA & data agreementQC.5Pilot order signedM
SystemInputOutputProtectiveCritical pathStochastic conditioningRed flag
First, validate the problem

Before the MVP: 17 interviews on facts (spend on protection, last disruption, who signs), 2 letters of intent, then a go / no-go (B.0).

The customer's time

The approval is decomposed to level 3. The CFO's evaluation (C.3.2) is a red flag: its time and odds are not ours.

One contract, reviewed once

Pilot and subscription terms together. Vendor registration runs in parallel, so it does not delay the order.

First contact 11 May 27, pilot order 15 Jun 27. Yellow = input functions, done by the customer. Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by hand09 / 17
D · How we deliver the pilot

The pilot in 26 working days: map first, then ask only what matters

Deliver the paid pilot, June – July 2027levels 3 and 4 · weekends shaded
14 Jun21 Jun28 Jun5 Jul12 Jul19 JulD.1 Kick-off & data request: 15 Jun 27 – 15 Jun 27, 1 working daysD.2.1 ERP export by the buyer: 16 Jun 27 – 22 Jun 27, 5 working daysD.2.2 Public hazard & credit data: 23 Jun 27 – 23 Jun 27, 1 working daysD.2.3.1 Sensor: rules on import: 23 Jun 27 – 23 Jun 27, 1 working daysD.2.3.2 Logic: thresholds: 24 Jun 27 – 24 Jun 27, 1 working daysD.2.3.3 Actuator: ask or estimate: 25 Jun 27 – 25 Jun 27, 1 working daysD.3 First-pass exposure map: 28 Jun 27 – 28 Jun 27, 1 working daysD.4.1 Sensitivity: 3–5 key data: 29 Jun 27 – 29 Jun 27, 1 working daysD.4.2 Buyer asks key suppliers: 30 Jun 27 – 30 Jun 27, 1 working daysD.4.3 Key suppliers answer: 1 Jul 27 – 12 Jul 27, 8 working daysD.4.4 Reminder by the buyer: 8 Jul 27 – 8 Jul 27, 1 working daysD.4.6 Mid-pilot check-in, CFO: 6 Jul 27 – 6 Jul 27, 1 working daysD.4.5 Answers in; typical values: 13 Jul 27 – 13 Jul 27, 1 working daysD.5 Update map, run options: 14 Jul 27 – 15 Jul 27, 2 working daysD.6.1 Sensor: 2nd analyst reads: 16 Jul 27 – 16 Jul 27, 1 working daysD.6.2 Logic: plausibility list: 19 Jul 27 – 19 Jul 27, 1 working daysD.6.3 Actuator: release: 20 Jul 27D.7 Present results to CFO: 20 Jul 27 – 20 Jul 27, 1 working daysanswers' quality → reviewrejected: back to D.5D.1Kick-off & data requestSD.2.1ERP export by the buyerID.2.2Public hazard & credit dataID.2.3.1Sensor: rules on importQD.2.3.2Logic: thresholdsQD.2.3.3Actuator: ask or estimateQD.3First-pass exposure mapSD.4.1Sensitivity: 3–5 key dataSD.4.2Buyer asks key suppliersSD.4.3Key suppliers answerIRed flagD.4.4Reminder by the buyerQD.4.6Mid-pilot check-in, CFOQD.4.5Answers in; typical valuesQD.5Update map, run optionsSD.6.1Sensor: 2nd analyst readsQD.6.2Logic: plausibility listQD.6.3Actuator: releaseMD.7Present results to CFOO
SystemInputOutputProtectiveCritical pathStochastic conditioningRed flag
Value of information

First a map from ERP, public data and typical recovery times (D.3). Then the sensitivity picks the 3–5 data that can change the choice.

Supplier answers: a red flag

8 working days on the critical path, done by third parties. A reminder and typical values protect them.

Two checks in series

Data quality (D.2.3) and four-eyes review (D.6), each split into sensor, logic and actuator.

26 wd ≈ 5 weeks, within the 4–6 weeks we promise. Then the invoice and the 30-day payment term (D.8). Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by hand10 / 17
E–F · Conversion and onboarding

Decided in 8 working days, live in 9

Convert and onboard, July – September 2027levels 2 and 3 · weekends shaded
19 Jul26 Jul2 Aug9 Aug16 Aug23 Aug30 Aug6 Sep13 Sep20 Sep27 SepD.7 Present pilot results: 20 Jul 27 – 20 Jul 27, 1 working daysE.1 Offer: level + start date: 21 Jul 27 – 22 Jul 27, 2 working daysE.2.1 Buyer & CFO weigh results: 23 Jul 27 – 29 Jul 27, 5 working daysE.2.2 Choose level & start date: 30 Jul 27 – 2 Aug 27, 2 working daysE.2.3 CFO sign-off: 3 Aug 27 – 3 Aug 27, 1 working daysE.3 Subscription signed: 4 Aug 27D.8 Pilot invoice, paid in 30 days: 21 Jul 27 – 20 Aug 27, 23 working daysE.4 Contract start: 30 Aug 27E.5 Yearly fee paid (30-day term): 30 Aug 27 – 28 Sep 27, 22 working daysE.6 Reminder if the fee is late: 30 Aug 27 – 28 Sep 27, 22 working daysF.1 Extend to all critical parts: 30 Aug 27 – 1 Sep 27, 3 working daysF.2 Recurring ERP export: 30 Aug 27 – 3 Sep 27, 5 working daysF.3 Thresholds, budget cap: 2 Sep 27 – 3 Sep 27, 2 working daysF.4 Event triggers (sensors): 6 Sep 27 – 7 Sep 27, 2 working daysF.5 Train buyer & CFO: 8 Sep 27 – 8 Sep 27, 1 working daysF.6 Go-live check: 9 Sep 27 – 9 Sep 27, 1 working daysF.7 Go-live: 10 Sep 27pilot value → conversion4 Aug30 Aug10 Sep18 working days of marginD.7Present pilot resultsOE.1Offer: level + start dateOE.2.1Buyer & CFO weigh resultsIRed flagE.2.2Choose level & start dateSE.2.3CFO sign-offIE.3Subscription signedMD.8Pilot invoice, paid in 30 daysE.4Contract startME.5Yearly fee paid (30-day term)IE.6Reminder if the fee is lateWF.1Extend to all critical partsSF.2Recurring ERP exportSRed flagF.3Thresholds, budget capSF.4Event triggers (sensors)SF.5Train buyer & CFOOF.6Go-live checkQF.7Go-liveM
SystemInputOutputProtectiveStandbyCritical pathStochastic conditioningRed flag
8 working days to decide

The contract was reviewed with the pilot order: the customer only chooses level and start date. It was 14 days.

The budget moves the start

It no longer blocks the signature. Signed 4 Aug, start 30 Aug, after the summer closure; yearly fee invoiced in advance.

Onboarding in 9 working days

Within our 10-day promise. The recurring ERP export (F.2) is the part we know least: every ERP is different.

Start date chosen by the customer: now or with the next budget year. The full ERP connector is a paid module. Dashed = standby function (reminder only if the fee is late). Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by hand11 / 17
G–H · How we maintain the service

Year 1: a product, not consulting

Deliver the service and renew, Sep 2027 – Aug 2028levels 2 to 4
SepOctNovDecJanFebMarAprMayJunJulAugG.1.1 Quarterly recalculation Q1: 19 Nov 27 – 26 Nov 27, 6 working daysG.1.2 Quarterly recalculation Q2: 21 Feb 28 – 28 Feb 28, 6 working daysG.1.3 Quarterly recalculation Q3: 19 May 28 – 26 May 28, 6 working daysG.1.4 Quarterly recalculation Q4: 17 Aug 28 – 24 Aug 28, 6 working daysG.2.1 Sensor: alerts, credit, lead times: 10 Sep 27 – 24 Aug 28, 250 working daysG.2.2 Logic: threshold rules: 10 Sep 27 – 24 Aug 28, 250 working daysG.2.3 Actuator: re-run, notify ≤ 2 wd: 10 Sep 27 – 24 Aug 28, 250 working daysG.3.1 Customer prepares the budget: 1 Oct 27 – 25 Nov 27, 40 working daysG.3.2 Budget allocation & curve: 22 Oct 27 – 25 Oct 27, 2 working daysG.3.3 Analyst review: 26 Oct 27 – 26 Oct 27, 1 working daysG.3.4 Decision meeting with CFO: 27 Oct 27 – 27 Oct 27, 1 working daysG.3.5 Customer implements: 28 Oct 27 – 22 Dec 27, 40 working daysG.3.6 Follow-up after 30 days: 25 Nov 27 – 25 Nov 27, 1 working daysG.4 Helpdesk, releases, backups: 10 Sep 27 – 24 Aug 28, 250 working daysG.4.2 Parameter library update: 17 Dec 27 – 23 Dec 27, 5 working daysG.5 Usage review, upgrade offer: 25 Feb 28 – 25 Feb 28, 1 working daysG.6 Health check (−120 days): 2 May 28 – 2 May 28, 1 working daysH.1 Renewal trigger (−60 days): 3 Jul 28H.2 Value review with CFO: 3 Jul 28 – 4 Jul 28, 2 working daysH.3 Auto-renewal, invoice year 2: 30 Aug 28decisions implemented → renewal3 Jul30 AugG.1Quarterly recalculationsG.2.1Sensor: alerts, credit, lead timesSG.2.2Logic: threshold rulesWG.2.3Actuator: re-run, notify ≤ 2 wdWG.3.1Customer prepares the budgetIG.3.2Budget allocation & curveSG.3.3Analyst reviewQG.3.4Decision meeting with CFOOG.3.5Customer implementsOG.3.6Follow-up after 30 daysQG.4Helpdesk, releases, backupsG.4.2Parameter library updateSG.5Usage review, upgrade offerOG.6Health check (−120 days)QH.1Renewal trigger (−60 days)MH.2Value review with CFOOH.3Auto-renewal, invoice year 2M
SystemInputOutputProtectiveStandbyMilestoneLogical linkStochastic conditioning
Review only by exception

Every quarter the engine recalculates; the analyst steps in only if the choice changes (G.1.1.4). Q1 is split into 6 steps (level 4).

The customer's budget sets our calendar

A start-to-start link: the CFO prepares the budget in October, our allocation comes in October.

The renewal is protected three times

Decision register (G.1.1.6), follow-up 30 days after the decision, health check 120 days before.

Dashed bars = standby functions, started only by an event. Quarters Q2–Q4 have the same structure as Q1. Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by hand12 / 17
Y2–Y5 and I · Repeat, then retire

Renewed every 30 August; the grave is deleted data

Years 2–5: the same functions as year 1level 2 · Yn = year 2 to 5
2029203020312032Y2.1 Quarterly recalculations x4: 30 Aug 28 – 21 Aug 29, 255 working daysY3.1 Quarterly recalculations x4: 30 Aug 29 – 21 Aug 30, 255 working daysY4.1 Quarterly recalculations x4: 30 Aug 30 – 21 Aug 31, 255 working daysY5.1 Quarterly recalculations x4: 1 Sep 31 – 20 Aug 32, 255 working daysY2.2 Event watch & on-event recalculation: 30 Aug 28 – 21 Aug 29, 255 working daysY3.2 Event watch & on-event recalculation: 30 Aug 29 – 21 Aug 30, 255 working daysY4.2 Event watch & on-event recalculation: 30 Aug 30 – 21 Aug 31, 255 working daysY5.2 Event watch & on-event recalculation: 1 Sep 31 – 20 Aug 32, 255 working daysY2.3 Annual budget allocation: 23 Oct 28 – 26 Oct 28, 4 working daysY3.3 Annual budget allocation: 22 Oct 29 – 25 Oct 29, 4 working daysY4.3 Annual budget allocation: 22 Oct 30 – 25 Oct 30, 4 working daysY5.3 Annual budget allocation: 22 Oct 31 – 27 Oct 31, 4 working daysY2.4 Support, releases & security: 30 Aug 28 – 21 Aug 29, 255 working daysY3.4 Support, releases & security: 30 Aug 29 – 21 Aug 30, 255 working daysY4.4 Support, releases & security: 30 Aug 30 – 21 Aug 31, 255 working daysY5.4 Support, releases & security: 1 Sep 31 – 20 Aug 32, 255 working daysH.3 Auto-renewal & invoice year 2: 30 Aug 28Y2.5 Value review & renewal (year 2 > 3): 30 Aug 29Y3.5 Value review & renewal (year 3 > 4): 30 Aug 30Y4.5 Value review & renewal (year 4 > 5): 1 Sep 31Y5.5 Closure notice: 1 Jun 32I.1 End of contract: 30 Aug 321 Jun 3230 Aug 32Yn.1Quarterly updatesSYn.2Event watchWYn.3Budget allocationSYn.4Support, releasesSYn.5Renewal, 30 AugMY5.5Closure noticeMI.1End of contractM
SystemStandbyMilestone
I · Decommission the customer, Aug – Sep 2032level 2
23 Aug30 Aug6 Sep13 Sep20 SepI.2 Final report & register: 25 Aug 32 – 27 Aug 32, 3 working daysI.1 End of contract: 30 Aug 32I.3 Export data, open format: 30 Aug 32 – 31 Aug 32, 2 working daysI.4 Confirm export, cut access: 1 Sep 32 – 1 Sep 32, 1 working daysI.5 Delete data + certificate: 2 Sep 32 – 15 Sep 32, 10 working daysI.6 Anonymised recovery times: 1 Sep 32 – 1 Sep 32, 1 working daysI.7 Final invoice, closure: 16 Sep 32 – 16 Sep 32, 1 working daysI.8 Lifecycle closed: 17 Sep 3230 Aug17 SepI.2Final report & registerOI.1End of contractMI.3Export data, open formatOI.4Confirm export, cut accessQI.5Delete data + certificateQI.6Anonymised recovery timesSI.7Final invoice, closureSI.8Lifecycle closedM
SystemOutputProtectiveMilestoneLogical link
The customer keeps the decision register and its data; we delete everything, backups included, with a certificate, and keep only anonymised recovery times if the contract allows. Old model versions retire in the quarterly releases (G.4.3).
Nominally the customer would keep renewing: we close at year 5 because it is the TEA horizon, and so the Gantt also shows the decommissioning. Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by hand13 / 17
Breadth, depth and red flags

Uneven depth shows what we know least

IDLevel-1 functionL1L2L3L4Flags
ADevelop the MVP1723– 2
BValidate & find leads149– 3
CSell the pilot155– 1
DDeliver the pilot18143 1
EConvert163– 1
FOnboard17–– 1
GService, year 116179
HRenew13––
Y2–Y5Service, years 2–5420––
IDecommission18––
ZCompany support16––
177 functions14807112 9
Red flags: three durations, not oneoptimistic · most likely · pessimistic
0 wd10 wd20 wd30 wd40 wdB.1.1–3Channels → first contact51040C.3.2CFO weighs the pilot2520D.4.3Key suppliers answer5820E.2.1Customer decides3540F.2Recurring ERP export2515A.2.3Credit-data connector6820A.4.3Protection cost library6820
Most likely = the nominal duration in the Gantt. Long tails: the CFO postpones, the ERP has no standard export. Also the whole MVP (A): 100 · 116 · 180 wd. In the model: triangular distributions.
Number of functions per level of decomposition for each level-1 function. Red flags = the functions we know least (most are done by others). Three-point durations in working days [assumptions]14 / 17
Criticalities we can already see

Listed now, modelled next

Half of the sale is decided by others

31 of the 61 working days on the critical path wait for the customer or the suppliers.

The first income depends on the MVP

Double link on the pilot kick-off, zero slack: an MVP delay moves pilot, contract and fee.

The customer's calendar rules

Budget cycle and deferred start: the signature arrives, the fee may not.

The customer creates the value

If the protections are not implemented (G.3.5), there is little to show at renewal.

Data errors propagate

Into map, proposal and decision: two checks in series (D.2.3 and D.6).

Standby functions have no frequency yet

How many events per customer per year? It drives the analyst's hours.

Deviations we already knoweach one becomes a branch in Klarisk
IDDeviationVariable for the model
AMVP is latedays of MVP delay
B.0.3No letters of intentletters obtained
C.3.2CFO postpones or says nochance of a yes; time (3 estimates)
D.6Review rejects the mapshare of rejections
D.4.3Suppliers do not answerresponse rate
E.2.1Pilot not converted (S3 → S7)conversion 40–80%
E.2.2Budget closed: start next yearshare of deferred starts
E.5Yearly fee paid latedays to collect
G.3.5Protections not implementedshare implemented
H.2Customer cancels (S6 → S7)renewal 80–92% a year
10 of the 15 deviations we know (Backup H). The 8 stochastic conditionings of the Gantt link these branches.
Conversion: paid pilots convert 60–90% (SaaStr, industry source), lowered to 40–80% to be prudent. Renewal: median 88% for B2B software (Benchmarkit 2025, industry survey). Other values: our assumptions15 / 17
What the analysis changed

It showed weak points, so we changed the process

SALESB.0Validate before the MVP

Interviews ask facts, not opinions, and a commitment.

target: 2 letters of intent
SALESB.0.3 · A.4.1Go / no-go after the interviews

Before, the interviews changed nothing in the process.

no confirmation, no engine
PILOTD.3–D.4Value of information

First the map, then only the 3–5 data that change the choice.

fewer questions to suppliers
CONTRACTC.3.4 · E.2One contract, reviewed once

Pilot and subscription terms in the same contract.

decision: 14 → 8 working days
BUDGETE.2.2 · E.4–5Flexible start, fee in advance

The budget moves the start; it no longer blocks the signature.

signature and start decoupled
PRICEC.2 · E.4Pilot paid in full

No longer deducted from the first yearly fee: its map is worth its price.

same as the TEA and the pitch
PROTECTIOND.4.6 · G.3.6 · G.6Protect the riskiest functions

CFO decision, implementation by the customer, renewal.

4 new protective functions
STRUCTUREStep 1Sales and relationship together

The method asks for the fewest interfaces.

2 interfaces fewer
CALENDARH.3 · Y2.5–Y4.5 · I.1Anniversaries on calendar dates

With 260 working days a year, the anniversary drifted.

renewal every 30 August
SERVICEG.1.1.4 · G.1.1.6Review by exception + register

Reviewing every update was consulting; the register proves the value.

7.5 vs 10.5 person-days a year
We did not change the idea or the customer. We rejected three alternatives: one-off analyses (they do not scale), ERP partners in year 1 (no partner without pilots), large groups (the field of Resilinc and Interos)16 / 17

Next: every function brings its variables into the TEA @ Risk

Durations9 red flagsthree estimates each, as triangular distributions
Branches15 deviationswith their probabilities, in the Klarisk model
Links8 conditioningsstochastic links between the branches
Founders' time10.6 · 6.5 · 7.5person-days per pilot, onboarding, customer-year
Thank you · Questions?
Brian CepeliMatteo FornaraAlessandro GazzaraPietro Gilli Incantalupo
17 / 17
Backup A · for questions

The MVP at level 3: all functions and links

A · Develop the decision engine: 23 level-3 functions + the milestonered = critical path · grey = logical links (FS, SS)
Jan 27FebMarAprMayJunA.1.1 ERP export template (parts, suppliers, sites, stock): 4 Jan 27 – 15 Jan 27, 10 working daysA.1.2 Supplier questionnaire (recovery time, other sites): 6 Jan 27 – 19 Jan 27, 10 working daysA.1.3 List of public data (hazard maps, credit scores): 4 Jan 27 – 11 Jan 27, 6 working daysA.1.4 Check the data model on the simulated company: 20 Jan 27 – 25 Jan 27, 4 working daysA.2.1 ERP import with validation rules: 26 Jan 27 – 16 Feb 27, 16 working daysA.2.2 Locate supplier sites on the hazard maps: 26 Jan 27 – 10 Feb 27, 12 working daysA.2.3 Connect to credit scores (paid data): 26 Jan 27 – 4 Feb 27, 8 working daysA.2.4 Online questionnaire and answer import: 26 Jan 27 – 8 Feb 27, 10 working daysA.3.1 Link product → part → supplier → site: 17 Feb 27 – 4 Mar 27, 12 working daysA.3.2 Impact of a stop, per site and cause: 5 Mar 27 – 22 Mar 27, 12 working daysA.3.3 Frequency of a stop, per site and cause: 9 Mar 27 – 24 Mar 27, 12 working daysA.3.4 Exposure map and ranking of critical parts: 25 Mar 27 – 5 Apr 27, 8 working daysA.4.1 Event tree for each part and option: 25 Mar 27 – 15 Apr 27, 16 working daysA.4.2 Monte Carlo simulation of yearly losses: 16 Apr 27 – 3 May 27, 12 working daysA.4.3 Cost of each protection option: 25 Mar 27 – 5 Apr 27, 8 working daysA.4.4 Best protection within the budget: 4 May 27 – 19 May 27, 12 working daysA.4.5 Sensitivity: which data change the choice: 20 May 27 – 31 May 27, 8 working daysA.5.1 Exposure-map report (what the pilot delivers): 6 Apr 27 – 19 Apr 27, 10 working daysA.5.2 Decision report for the CFO: 20 May 27 – 2 Jun 27, 10 working daysA.5.3 Web dashboard and user access: 6 Apr 27 – 3 May 27, 20 working daysA.6.1 Regression tests on reference cases: 3 Jun 27 – 14 Jun 27, 8 working daysA.6.2 Plausibility check against a benchmark: 3 Jun 27 – 8 Jun 27, 4 working daysA.6.3 Security and GDPR set-up: 4 May 27 – 17 May 27, 10 working daysA.7 MVP ready: 15 Jun 2715 JunA.1.1ERP export template (parts, suppliers, sites, stock)SA.1.2Supplier questionnaire (recovery time, other sites)SA.1.3List of public data (hazard maps, credit scores)SA.1.4Check the data model on the simulated companyQA.2.1ERP import with validation rulesSA.2.2Locate supplier sites on the hazard mapsSA.2.3Connect to credit scores (paid data)SRed flagA.2.4Online questionnaire and answer importSA.3.1Link product → part → supplier → siteSA.3.2Impact of a stop, per site and causeSA.3.3Frequency of a stop, per site and causeSA.3.4Exposure map and ranking of critical partsSA.4.1Event tree for each part and optionSA.4.2Monte Carlo simulation of yearly lossesSA.4.3Cost of each protection optionSRed flagA.4.4Best protection within the budgetSA.4.5Sensitivity: which data change the choiceSA.5.1Exposure-map report (what the pilot delivers)SA.5.2Decision report for the CFOSA.5.3Web dashboard and user accessSA.6.1Regression tests on reference casesQA.6.2Plausibility check against a benchmarkQA.6.3Security and GDPR set-upQA.7MVP readyM
SystemProtectiveMilestoneCritical pathLogical linkRed flag
Functions off the red path have slack before the signature (E.3): sensitivity A.4.5 2 working days; dashboard, exposure map, cost library 20; online questionnaire A.2.4 82. Durations: our nominal estimates in working days [assumptions]. Start date 4 Jan 2027 chosen only to build the calendar. The Gantt is computed from our model, not drawn by handBackup A
Backup B · for questions

Function types, and what the protective functions protect

TypeWhat it isElementary functions
S · SystemWork of Nexora, of the engine or of the team62
I · InputWhat comes from outside: customer, suppliers, data providers14
O · OutputWhat we deliver, or what the customer does with our decision11
Q · ProtectiveChecks and barriers that protect the function they are linked to28
W · StandbyDesigned and ready, started only by an event: dashed over their active period8
M · MilestoneStep between two states16
TotalHuman 38 · technological 57 · organisational 28 (milestones excluded)139
They protectProtective functions (Q)
The engine is rightA.1.4 data model checked on the simulated company · A.6.1 regression tests · A.6.2 plausibility check against a benchmark · G.4.3 tests at each release
The customer's dataD.2.3 quality check in the pilot · D.4.4 reminder to suppliers · D.4.5 typical values for missing answers · G.1.1.2 check at each update
The decision we deliverD.6 four-eyes review · G.1.1.4 change check · G.3.3 review of the budget split · F.6 go-live check
Conversion and renewalD.4.6 mid-pilot check-in · G.1.1.6 decision register · G.3.6 follow-up at 30 days · G.6 health check at −120 days
The team's timeB.3.3 qualification gate before any on-site visit · B.0.3 go / no-go before the decision engine
Data and liabilityC.4 NDA and data agreement · A.6.3 GDPR set-up · G.4.4 backups · I.4 export confirmed before deletion · I.5 certified deletion · Z.4 GDPR · Z.2 insurance
The paymentE.6 reminder if the yearly fee is late (a standby function, like Z.6 incident response)
Function types from the course (slides 315–318), plus standby functions. Counts from the modelBackup B
Backup C · for questions

Sensor, logic and actuator

FunctionSensorLogicActuator
D.2.3 · Data quality check (pilot)Validation rules on the ERP import and the public dataCompleteness and consistency thresholdsThe analyst asks for missing data or uses typical values
D.6 · Four-eyes reviewA second analyst reads map and proposalPlausibility checklist: benchmarks, outliersRelease, or back to D.5
G.2 · Event watchHazard and weather alerts at supplier sites, credit-score drops, lead times growing in the ERPThreshold rules: the event falls in a site's hazard zone or the score dropsRe-run the model and warn the buyer within 2 working days
G.1.1.4 · Change check (quarterly)The engine compares the new choice with the previous oneThreshold: protection of at least one part, or budget beyond a tolerance, changesAutomatic report if nothing changes; otherwise the analyst reviews
G.6 · Check before renewal (organisational)Decision register and use of the serviceThreshold: few protections implemented, or low useAction plan with the buyer before the value review
H.1 · Renewal triggerContract calendar60-day ruleValue review with the CFO (H.2)

In the event watch the sensor (G.2.1) always works, so it is a system function; logic and actuator (G.2.2, G.2.3) start only with an event, so they are standby functions.

These are the functions where an error changes the decision delivered to the customerBackup C
Backup D · for questions

Steps that are not nominal, also backwards

StepWhen it happensWhat starts
S2 → S1Negative qualification (B.3.3)The contact goes back to the channels' pool
S3 → S7The pilot does not become a contract (E.2.1)Short decommissioning: export and deletion of the pilot data (I.3–I.5); new contact at the next budget
S3 → S4, deferred startThis year's budget is closed (E.2.2)Sign now; start and invoice with the new budget year
S5 → S5e → S5An alert hits a supplierG.2.1 → G.2.2 → G.2.3, then back to the quarterly cycle
S5 → S5m → S5Engine releaseG.4.3; the service stays on, the release passes the regression tests
S6 → S7The customer cancels at renewal (H.2)Full decommissioning (I.1–I.8) before the end of the horizon
S5 → S8 → S5Security incidentZ.6: access suspended, customers and Garante notified within 72 hours; restart after checks
D.6 → D.5The four-eyes review rejects the mapBack to updating the map (2–3 more days)
The Gantt shows only the nominal version. These steps are declared here; their probabilities will be estimated in the Klarisk modelBackup D
Backup E · for questions

Slack: how far each function can slip before the signature moves

IDFunctionEarliest startLatest startSlack (wd)
A.4.5Sensitivity & value of information20 May 2724 May 272
C.3.4Legal review of one contract (pilot + subscription terms)2 Jun 274 Jun 272
D.2.2Public hazard & credit data at supplier addresses23 Jun 2725 Jun 272
D.4.4Reminder by the buyer8 Jul 2713 Jul 273
A.6.2Plausibility check vs benchmark (MGI 1 in 3.7 yrs)3 Jun 279 Jun 274
C.4NDA & data processing agreement (pilot + subscription)2 Jun 278 Jun 274
D.4.6Mid-pilot check-in with buyer & CFO (expectations, budget timing)6 Jul 2713 Jul 275
A.1.3Map public data sources (ISPRA, INGV, credit scores)4 Jan 2712 Jan 276
B.0.117 interviews on facts: spend, last disruption, who signs4 Jan 2727 Jan 2717
B.0.3Go / no-go: problem confirmed, keep building?1 Mar 2724 Mar 2717
A.2.2Geocode supplier sites + hazard lookup (IdroGEO, INGV)26 Jan 2719 Feb 2718
A.3.4Exposure map & criticality ranking25 Mar 2722 Apr 2720
A.4.3Protection cost library (stock, 2nd source, insurance)25 Mar 2722 Apr 2720
A.5.1Exposure-map report (pilot deliverable)6 Apr 274 May 2720
A.5.3Web dashboard & user access6 Apr 274 May 2720
A.6.3Security & GDPR set-up (EU hosting, backups, DPA)4 May 271 Jun 2720
A.2.3Credit-risk data connector (Cerved / CRIF)26 Jan 2725 Feb 2722
A.2.4Questionnaire web form & answer import26 Jan 2720 May 2782
Slack = how many working days a function can be late before the signature (E.3) moves. Computed on the Gantt model. Functions not listed are on the critical path (slack 0). Between signature and contract start: 18 working daysBackup E
Backup F · for questions

How much work one customer asks of the team

ItemPerson-daysWhat it includes
Each pilot, converted or not10.6Qualification, visit, proposal, delivery, review, presentation, offer
Onboarding a new customer6.5Scope extension, ERP export, thresholds, sensors, training, check
One active customer for a year7.5 (10.5 without review by exception)Updates, events, budget, support, value review and renewal
Fixed work of the company per year62Channels, parameter library, releases, administration
Scenario S3 (phase 1) of the preliminary TEA: workload vs capacity
Year 1: 6 pilots, 4.0 customers182 of 880 person-days · 21%
Year 2: 9 pilots, 8.7 customers263 of 880 person-days · 30%
Year 3: 14 pilots, 15.8 customers379 of 880 person-days · 43%
Year 4: 14 pilots, 21.8 customers424 of 880 person-days · 48%
Year 5: 14 pilots, 26.9 customers462 of 880 person-days · 52%

Four full-time founders ≈ 880 person-days a year [assumption]. Pilots, onboarding, customers and fixed work take 30% (year 2) to 52% (year 5) of the time [estimate]: the limit is finding customers, not time.

Person-days given to each function done by the team [assumptions]. Today the founders' time is not counted in the TEA: it will be in the TEA @ RiskBackup F
Backup G · for questions

The variables each function brings into the TEA @ Risk

FunctionVariableValue todayLabel
B.1Pilots per year found by the founders1–4 in year 1, then 3–8[assumption]
B.0Interviews confirming the problem; letters of intent17 interviews; target 2 letters[to verify]
B.3.3, C.3.2Share of contacts that qualify and accept the pilotto estimate[to verify]
C.1 · C.2Travel per pilot · pilot price€300–600 · €2,500[assumption]
D.4.3Suppliers' response rateto estimate[to verify]
D.8.2Days to collect the payment30[assumption]
E.1Yearly fee€6–15k, most likely €9k[assumption]
E.2.1Pilot → contract conversion40–80%SaaStr (industry), lowered
B.2 → E.3Sales cycle85 days nominal; 124 as reference[estimate]; industry
FOnboarding effort per customer (≤ 10 working days)6.5 person-days[assumption]
G.1.1.4Updates needing the analyst · cloud per customer1 in 4 · €200 a year[assumption]
G.2Events per customer per yearto estimate[to verify]
G.5 · H.2Growth of staying customers · renewal0–8% · 80–92% a yearBenchmarkit (industry)
ZFixed costs€15k in year 1, then €9k[assumption]
Red flags enter with the three-point durations (slide 14); deviations as branches with probabilities. Labels as in our project report: [assumption] = our choice, [estimate] = our calculation, [to verify] = to check, industry = vendor or press sourceBackup G
Backup H · for questions

The 15 deviations we already know

FunctionDeviationEffect on the processVariable for the model
AMVP development is lateMoves D.1 and with it pilot, conversion and first fee (no slack)Days of MVP delay
B.0.3No letter of intent, few confirmationsNegative go / no-go: revise the offer before building the decision engineLetters of intent obtained
B.1A channel brings no contactsThe first contact (B.2) comes laterContacts per channel
B.3.3Negative qualificationBack to S1; time spent without a pilotShare of qualified contacts
C.3.2The CFO postpones or refusesLater pilot order, or no pilotChance of a yes; time (three estimates)
D.4.3Suppliers do not answer, or answer badlyTypical values with wider ranges (D.4.5); a less precise mapResponse rate
D.6The review rejects map or proposalBack to D.5, 2–3 more daysShare of rejected reviews
E.2.1The customer does not convertS3 → S7 with short decommissioningConversion 40–80%
E.5The yearly fee is paid lateReminder (E.6); cash arrives laterDays to collect
E.2.2This year's budget is closedSign now, start and fee with the new yearShare of deferred starts
F.2The ERP has no standard exportOnboarding beyond 10 daysDays of onboarding
G.2Alert on a supplierEvent re-run and analyst hoursEvents per customer per year
G.3.5The customer does not implementLittle value to show at renewalShare of decisions implemented
H.2The customer cancelsS6 → S7 before the end of the horizonRenewal 80–92% a year
Z.6Security incidentEmergency shut-down, notice within 72 hoursIncident frequency [to verify]
The operational Gantt (how things really go) will be built by comparing this nominal Gantt with the first pilots. These deviations are the starting pointBackup H